Sunday, April 13, 2008

High School Renovation Project 4/10/08

General Comments

The MHS Project Management Advisory Committee met on Thursday 4/10/08 to review the status of the High School Renovation Project.

There continues to be good progress made on the project, and it is basically on schedule, will completion expected by the end of the summer.

Work on the track portion should resume in the next few weeks, when the loam piles have warmed completely, and have dried out a bit. They will then spread the loam, and install the sprinkler system. The sod will be put down after that, and allowed to sit for a while before it is used. Conduit to feed electrical and data feeds to the press box will be fed under the parking lot during the April vacation.

The actual track surface will not be installed until sometime in the summer. The top layer of track surface will bond better to the lower surface when the ground is good an warm. The warmer the better, so they will not do it until June or July. It will all be complete in time for start up of school in the fall.


The interior work is progressing, The music room is almost complete, and the students will move into it in a week or so.


Some of the interior rooms are nearing completion, and classes are moving into them, freeing up more rooms to be worked on.


Minor Problems


The committee reviewed and approved seven different change orders totaling $13,343. These are the typical types of change orders that arise during a renovation project. They included items such as the need for additional sprinkler heads in some new closets, adding sprinkler heads above the ceilings since the ceilings had to be lowered to accommodate piping changes, increasing the snow loading specification for the pressbox, etc.


Major Problems


Three issues have come up that are more serious due to the cost factors involved.


* We are adding new fire detection points to the fire alarm system. These points are being added to provide detection in various sections of the renovation project, including in the mechanicals in the music room and in various areas of room 4. It was not anticipated, but it was discovered that the fire annunciator panel at the front of the building has been maxed-out, and will need to be expanded to add new detection points to the system. It is important that the points be properly identified on the panel, to allow the fire department to quickly develop a plan of action when they respond to a call at the building.


The various people involved are looking at our alternatives at this point in time. One course of action would be to do the minimum amount necessary to get the planned changes identified on the panel. This would leave the panel in a maxed-out state, and require major changes if additional points were needed in the future.


Another alternative would be to expand the panel significantly to allow for future point expansion. This would require that the existing system be taken out and replaced by a completely new system. This will cost a lot more, but has the advantage of allowing us to change the technology that is used to allow for more open source technology, and multiple source sourcing.


The cost penalty for this issue is not known for sure, but it is being investigated. A rough guesstimate is that it is somewhere between $17K and $40K depending on which approach is chosen.


* The budget included $30K for the foundation work for the bleachers. This figure was based on typical foundations for similar bleachers.


It turned out that there are special problems with our particular installation, and a more costly foundation is needed. The basic problem is that there is very little room between the rear of the bleachers and the fence, and the elevation change is steep in that area. Because of this, the design engineer has specified that we install a retaining wall at the rear of the foundation concrete pad to insure that there is the proper support.


The first estimate for the more elaborate foundation was $75K, or $45K over the budgeted amount. We reviewed this issue in detail at the meeting. The final decision was that we asked the people involved to go back and see if they can come up with a design that uses a full size retaining wall at the rear of the press box, but uses a smaller or no retaining wall at all in the other areas of the bleachers where the distance from the structure to the fencing will be greater.


* We received a bill from the water utilities group for a new service entrance fee. This fee is based on anticipated annual usage, and was $22,691 for our filed irrigation system.


We spent a lot of time discussing this fee, and trying to find alternatives. We are going to look into the feasibility of installing a well to replace or supplement the town water service, with the expectation that this would reduce the entrance fee and/or reduce our annual water charges.


Mike Trojano had received a rough guesstimate of a typical well installation for a service of this type. The cost was $15K for the well or wells plus $5K for design/consultation services, for a total of $20K. In some cases, the cost could be higher if the well(s) need to be a lot deeper, if water treatment is needed, or if storage system(s) are needed to provide that the flow rates.


Several committee members questioned the feasibility of being able to get a well in this area that will have the needed gallons per minute flow capacity to meet the needs of the system. They are going to review the geologic maps of the area to get a rough estimate of the difficulties that can be expected to be encountered.


We are going to have another meeting in two weeks to review each of these issues.


Budget Summary


We were doing relatively well with the budget, until we hit these various cost adders. Business Administrator Mike Trojano will be putting together another cost roll-up for our next meeting, but this is where I think that we are based on a rough update of the previous roll-ups.


We had been at around $250K of unallocated contingency funds at the last roll-up. Subtracting out $13K for the approved changes, $35K for the annunciator panel, $30K for extra bleacher foundations, $5K for a negotiated water entrance fee, and $20K for a well for irrigation, leaves about $145K of unallocated contingency funds.


There is another large issue that is pending, and this is that many of the doors that we had thought had been included in the bid process were actually not part of the bid. The only doors that were included were ones that were attached or next to areas that were being worked on separately. Doors for rooms that were not otherwise being renovated were not included.


The cost for renovating these extra doors is still being scoped out. Many of them are very expensive to renovate since they are non-standard sized and new door frames are needed to get new doors installed.


It is my opinion that renovating the doors is one of the higher priorities of the overall project. The current doors cannot be locked from the inside, and in a school lock-down mode, the occupants of the room would have to go into the corridors to lock the doors, thus exposing them to any potential threats. Adding more doors for the project could be as much as $50K-100K.


This lack of unallocated contingency is getting very tight for this portion of the project, as there are still a few areas that have not even been touched as of yet. There may be more unanticipated problems to be found.


We are carrying $82K for parking improvements in the budget, and we have not tapped in to this at all yet. We have done no work so far in designing what will be done for parking improvements. This is an area that could be a safety valve if needed to accommodate unanticipated expenditures. If we have to cut something from the project, then this might be an area that could be attacked.


We should have a better idea on the overall project costs when we meet again in two weeks.

Wednesday, April 9, 2008

Milford School Board 4/7/08

MESSA

The meeting started with Deb Hayes from the High School talking in public comment as a representative from MESSA (Milford Educational Support Staff Association). This is the bargaining unit that has been in negotiations with the School Board for a year and a half. The group had previously requested that the entire school board meet with them directly to negotiate the contract, and the board had subsequently turned down their request. Ms. Hayes reiterated their request and asked the board to reconsider the decision. Chairman Bragdon indicated that the board would probably bring this up at the previously scheduled non-public session that would be held at the end of the meeting.

Bob Willette Presentation

Peter Bragdon presented Bob Willette with a granite plaque as a memento of his five years of service on the board. Lorna Willette was also there to help with the ceremony.

Superintendent's Report

Bob Suprenant had these comments:

* The Middle School Math Counts team entered the Ultimate Math Competition, and the team achieved Gold Level status. This means that at least 12 members of the team scored 80% or higher on the test. There will be a banner posted in the school to commemorate the achievement.

* 16 High school students were named Granite State Scholars. They will be eligible to apply for scholarships if they meet certain criteria, such as attending particular state schools.

* There were 9 winners at the State History Day competition.

* 10 Students were in the New Hampshire Science day competition
Liam Hurley won first in the state Skills competition in the carpentry section, and he will be going to the national competition (which is usually in Kansas City, but I'm not sure about this year).

* 9 High School Students did well at the state FBLA Future Business Leaders of America competition, including Joe Stagnone who won 1st place in the accounting 2 competition.

* Libby Wehrle-Anderson is sponsoring a Teen Alcohol Use Forum on 6/9/08 at the Middle School.

* The Bales Study Committee is having a forum to receive public input regarding anyone's thought about potential futures uses for the Bales facility, to be held at the Selectman's room in Town Hall.

* Teachers and Administrators have been doing a lot of work at reviewing the NECAP test results. They are completing their findings, and Laurie Johnson will be presenting them at an upcoming meeting.

* The District job fair was held on 3/20/08. There were 101 initial interviews conducted at the fair, with follow-on interviews scheduled for some candidates. There are only 13 openings right now, which is a bit lower than what we have seen in the past few years. A few of the openings might be difficult to fill, with 3 in math and 2 in science at the high school.

* Bob Suprenant and Burt Becker went to Concord to testify on the subject of Senate bill 530 regarding education funding. They recommended that the funding for temporary classrooms be put back in the bill, and that new kindergarten construction aid be done at the 100% level instead of the planned 75% level.
The High School graduation will be held on 6/14/08 at 10:00 am in the Hampshire Dome since the football field will not be available this year. Thanks to Rick Holder of Hampshire Hills for making this happen - the Hampshire Dome will be a much better venue than the High School Gym which was the alternate choice.

Writing Across the Curriculum

Ms. Jackie Theriaque gave a presentation regarding the John Collins "Writing Across the Curriculum" program. This is a structured approach to try to incorporate writing skill improvement as part of all curriculum activities. For example, if a teacher is working with the class on a math unit, then she might include a writing assignment at the same time.

One aspect of this process is to include the concept of "Focused Correction Areas" FCAs for assignments. In this approach, the students are told in advance which particular portions of the writing assignment will be graded, and what the weightings will be. For example, one FCA might be proper capitalization with a weighting of 20%. The students will then know to focus on making sure that their capitalization is correct, and not worry about a non-graded area such as word choice. The FCAs are rotated during the year to insure that all grade level expectations are covered during the school year.

There are also permanent FCAs which apply for all writing assignments. These vary by grade level and for individual capability. They are set at a level where the student can be reasonably expected to be able to meet them at all times.

Committee Reports

There were few reports from the standard committees, except that Lori Pitsas made a summary presentation regarding the status of the MAFC Milford Athletics Fundraising Committee.

* April 17th, 7PM, at the High School cafeteria. This is being put on and being promoted by the High School Football Boosters group. Tickets are $8 in advance, or $10 at the door.

* Golf Tournament, Friday August 22nd, at Amherst Country Club.

* Road race in the fall, perhaps in early October near the date of the pumpkin festival

The fundraising group is continuing to look for donations of cash or in-kind items.

Lori mentioned that there are about 100 students on the track team at the Middle school, and about 70 on the track team at the High school.

Bob Suprenant mentioned that he had submitted Lori's name to the New Hampshire School Administrators Association NHSAA in nomination for the "Champions for Children" award for the Southwest district. Someone from Peterborough won the district nomination, but Lori was a well-deserved candidate.

CIP Capital Improvement Plan Committee

I was appointed as the School Board rep to the CIP. Peter Bragdon had been the rep on this committee for the past few years, but he felt that he could not fit it into his schedule this year. The purpose of the committee is to try to set up a unified capital improvement plan for the next few years (5?) to help in establishing priorities on capital spending.

After the meeting, I learned that there will be a more inclusive meeting set up this year to try to include most of the stakeholders in the discussion of capital planning. All 5 School Board members will be invited to the expanded meeting.

Water Utilities Entrance Fee Charge


We received a bill from the Milford Water Utilities for an Entrance Fee charge for the new irrigation system for the fields under construction. This is a fee that none of us had ever heard of before now, and it was not in the budget. The fee was assessed at $22,691, so it is not an insignificant issue.

We discussed this at some length, with the outcome that we directed the Superintendent to meet with the water utilities folks to see what our options might be.

Len Mannino suggested that we look into drilling a well to replace or supplement the water to be obtained from the town system. This might help with lowering the Entrance fee, and it should help with lowering the amount that we pay for water on an ongoing basis. This will be researched by the High School Renovations committee, along with the district administration.

Policy Review

Our ongoing review of policies continued, with policies relating to Instruction, School Calendar, and Length of School Day going to first reading, and Controvertial Issues not going to first reading. Some members wanted some more time to reflect on the Controversial Issues policy before moving it to first reading.

PEG Committee

John Parker was appointed to be the School Board rep to the PEG (Public/Education/Government) cable access committee.

School Board Goals


We reviewed the goals that were suggested at the previous meeting, and decided to create goals for these topics for the 08/09 School Board term.

* Develop a plan for a temporary solution for providing public kindergarten starting in the 09/10 school year. This should be completed in time to have it as part of the warrant for next year.

* Develop a plan for a permanent solution for providing public kindergarten, probably starting in the 10/11 school year. This should be completed in time to have it as part of the warrant for next year.

*
Complete contract negotiations with the Teachers bargaining unit in time for a warrant article for next year.

*
Complete contract negotiations with MESSA Milford Educational Support Staff Association in time for a warrant article for next year.

* Negotiate with Mason to provide educational support for their students on a tuition basis, probably starting in the 09/10 school year.

* Learn more about the standardized testing process, assess what we are doing, and decide if we need to do something different.

These items were also discussed, but were not set up as items to be tracked on a goal basis:

* Provide oversight on the high school renovation project.

* Develop action plans based on the results obtained from the Bales study committee which is expected to provide their final report at the second meeting in June.

* Provide oversight on the subdivision of the Heron Pond property.

* Modify the district policy manual to match the structure of the New Hampshire School Boards Association model policy manual.

* Investigate the impact of the increase of retirement account spending at the state level.

* Work to minimize the impact of gang development in Milford.