Sunday, April 13, 2008

High School Renovation Project 4/10/08

General Comments

The MHS Project Management Advisory Committee met on Thursday 4/10/08 to review the status of the High School Renovation Project.

There continues to be good progress made on the project, and it is basically on schedule, will completion expected by the end of the summer.

Work on the track portion should resume in the next few weeks, when the loam piles have warmed completely, and have dried out a bit. They will then spread the loam, and install the sprinkler system. The sod will be put down after that, and allowed to sit for a while before it is used. Conduit to feed electrical and data feeds to the press box will be fed under the parking lot during the April vacation.

The actual track surface will not be installed until sometime in the summer. The top layer of track surface will bond better to the lower surface when the ground is good an warm. The warmer the better, so they will not do it until June or July. It will all be complete in time for start up of school in the fall.


The interior work is progressing, The music room is almost complete, and the students will move into it in a week or so.


Some of the interior rooms are nearing completion, and classes are moving into them, freeing up more rooms to be worked on.


Minor Problems


The committee reviewed and approved seven different change orders totaling $13,343. These are the typical types of change orders that arise during a renovation project. They included items such as the need for additional sprinkler heads in some new closets, adding sprinkler heads above the ceilings since the ceilings had to be lowered to accommodate piping changes, increasing the snow loading specification for the pressbox, etc.


Major Problems


Three issues have come up that are more serious due to the cost factors involved.


* We are adding new fire detection points to the fire alarm system. These points are being added to provide detection in various sections of the renovation project, including in the mechanicals in the music room and in various areas of room 4. It was not anticipated, but it was discovered that the fire annunciator panel at the front of the building has been maxed-out, and will need to be expanded to add new detection points to the system. It is important that the points be properly identified on the panel, to allow the fire department to quickly develop a plan of action when they respond to a call at the building.


The various people involved are looking at our alternatives at this point in time. One course of action would be to do the minimum amount necessary to get the planned changes identified on the panel. This would leave the panel in a maxed-out state, and require major changes if additional points were needed in the future.


Another alternative would be to expand the panel significantly to allow for future point expansion. This would require that the existing system be taken out and replaced by a completely new system. This will cost a lot more, but has the advantage of allowing us to change the technology that is used to allow for more open source technology, and multiple source sourcing.


The cost penalty for this issue is not known for sure, but it is being investigated. A rough guesstimate is that it is somewhere between $17K and $40K depending on which approach is chosen.


* The budget included $30K for the foundation work for the bleachers. This figure was based on typical foundations for similar bleachers.


It turned out that there are special problems with our particular installation, and a more costly foundation is needed. The basic problem is that there is very little room between the rear of the bleachers and the fence, and the elevation change is steep in that area. Because of this, the design engineer has specified that we install a retaining wall at the rear of the foundation concrete pad to insure that there is the proper support.


The first estimate for the more elaborate foundation was $75K, or $45K over the budgeted amount. We reviewed this issue in detail at the meeting. The final decision was that we asked the people involved to go back and see if they can come up with a design that uses a full size retaining wall at the rear of the press box, but uses a smaller or no retaining wall at all in the other areas of the bleachers where the distance from the structure to the fencing will be greater.


* We received a bill from the water utilities group for a new service entrance fee. This fee is based on anticipated annual usage, and was $22,691 for our filed irrigation system.


We spent a lot of time discussing this fee, and trying to find alternatives. We are going to look into the feasibility of installing a well to replace or supplement the town water service, with the expectation that this would reduce the entrance fee and/or reduce our annual water charges.


Mike Trojano had received a rough guesstimate of a typical well installation for a service of this type. The cost was $15K for the well or wells plus $5K for design/consultation services, for a total of $20K. In some cases, the cost could be higher if the well(s) need to be a lot deeper, if water treatment is needed, or if storage system(s) are needed to provide that the flow rates.


Several committee members questioned the feasibility of being able to get a well in this area that will have the needed gallons per minute flow capacity to meet the needs of the system. They are going to review the geologic maps of the area to get a rough estimate of the difficulties that can be expected to be encountered.


We are going to have another meeting in two weeks to review each of these issues.


Budget Summary


We were doing relatively well with the budget, until we hit these various cost adders. Business Administrator Mike Trojano will be putting together another cost roll-up for our next meeting, but this is where I think that we are based on a rough update of the previous roll-ups.


We had been at around $250K of unallocated contingency funds at the last roll-up. Subtracting out $13K for the approved changes, $35K for the annunciator panel, $30K for extra bleacher foundations, $5K for a negotiated water entrance fee, and $20K for a well for irrigation, leaves about $145K of unallocated contingency funds.


There is another large issue that is pending, and this is that many of the doors that we had thought had been included in the bid process were actually not part of the bid. The only doors that were included were ones that were attached or next to areas that were being worked on separately. Doors for rooms that were not otherwise being renovated were not included.


The cost for renovating these extra doors is still being scoped out. Many of them are very expensive to renovate since they are non-standard sized and new door frames are needed to get new doors installed.


It is my opinion that renovating the doors is one of the higher priorities of the overall project. The current doors cannot be locked from the inside, and in a school lock-down mode, the occupants of the room would have to go into the corridors to lock the doors, thus exposing them to any potential threats. Adding more doors for the project could be as much as $50K-100K.


This lack of unallocated contingency is getting very tight for this portion of the project, as there are still a few areas that have not even been touched as of yet. There may be more unanticipated problems to be found.


We are carrying $82K for parking improvements in the budget, and we have not tapped in to this at all yet. We have done no work so far in designing what will be done for parking improvements. This is an area that could be a safety valve if needed to accommodate unanticipated expenditures. If we have to cut something from the project, then this might be an area that could be attacked.


We should have a better idea on the overall project costs when we meet again in two weeks.

Friday, March 14, 2008

High School Renovation Project

The MHS Project Management Advisory Committee held their monthly meeting yesterday to review the status of the ongoing renovations at the High School. Everything seems to be moving along well, with the overall project appearing to be on budget and on schedule.

Track and Field Update

Good progress was made on the track and field portion of the project during the fall months. Most of the major field work was completed, the drainage was installed, some fencing was put up, old bleachers were torn down, excess loam was removed from the site, lights were moved, subsurface and base coat for the track were installed, and the foundation for the storage building was installed.

Work has stopped on the site for the winter, except that the ATC construction program will be starting to construct the storage building soon. When the weather improves, they will start up again. Some of the major activities to be done include finishing off the track surface, building an appropriate foundation and installing bleachers, installing the press box, electrical and data feeds to the press box and scoreboard, and installing sod.

Most of the work should be completed by late spring or early summer. The football field will be rested for a while to allow the sod to take. It is expected that the field will be in great shape in time for the next football season.

High School Renovations Update

There are a number of renovation activities that will occur in the High School. Some activities have occurred over the past couple of months and will continue through the school year, but most of the activity will occur during the next summer.

The band room renovation is coming along well. It was gutted, new walls put up, stage storage area was constructed, stage handicapped lift area constructed, drainage put in, and practice rooms were created. The instrument storage system will be installed soon.

There are several interior rooms that are in progress. We ran into a minor snag in a couple of the rooms in that the roof supports turned out to be inverted wooden trusses instead of steel as had be expected. Some rooftop units were being installed, so they had to figure out a way to beef up the support structure to handle all the loads. They did come up with an approach that is safe and relatively inexpensive.

Bales Roof

The contract for the replacement of the Bales roof was given to Turnstone Corp, the construction manager for the high school project. The work will be done next summer.

Financial Update

The high school project is largely a renovation project, and it is always difficult to be exact on the costs up front since you never know what you are going to run into. There have been some items that were more expensive than expected and others that were lower, but in total, our best estimate at this time is that we have roughly $200k that is not spoken for as of yet, out of the $4,900k total project budget. There are quite a few items that still have place holder values in the cost roll-up, so this is subject to considerable change as we go through the project. In very rough numbers, we have committed spending of about $4,400k so far, with another $500k remaining to be committed.

The project management committee has worked well at making decisions to keep the project on budget. Priority decisions have been made, and in my opinion, good choices have been made.

The project seems to be in good financial shape at this point, with the majority of the big cost items mostly set, with only minor activities still up in the air.

Friday, October 12, 2007

High School Renovation Project

The MHS Project Management Advisory Committee met last night to review the status of the Milford High School renovation project.

Schedule

Leighton White is making excellent progress on the field work. The weather has been favorable, and the on-site materials have been relatively easy to work with. Everything seems to be tracking on schedule to this point. They are going to go as long as they can before the weather turns against them. They expect to have most of the significant site work done before winter. A couple of big items that will hold until the spring are the top surface on the track and the sod for the fields. One item that might get done this fall or it might wait for the spring is the rough surface underlayment for the track. This will depend on the weather.

Bleachers

The committee reviewed the bids that came in for bleachers. We had long discussions on the pros and cons of the various alternatives, but in the end, we decided to recommend to the School Board that we purchase the seven-year-old used bleachers that came from Adelphi University that are currently being stored in New Jersey. They are available from Seating Solutions. The company is headquartered in Commack, NY, but the bleachers are being stored in Newark, NJ.

As of now, the configuration will consist of seating for roughly 1,000 people on one side only with no visitors side. This is not a final decision, but based on cost issues, it seems like it is the right thing to do. Once we have a better handle on the overall costs for the project, we will revisit this since the general consensus is that breaking up the bleachers into a home and a visitors side is a better alternative.

We have $210k in the budget for bleachers and press box, and this alternative will be about $179k. This savings will help to make up some of the overages that we have seen elsewhere.

Fencing

We received three bids for fencing, and the committee voted to recommend to the School Board that the work be awarded to the low bidder for $47,525. Penney Fence from Londonderry was the low bidder, but I did not find a web site for them.

The fencing budget was $40k, so we are over budget in this area. There were some significant changes to the plan recently where the state environmental review required us to add more fencing around the detention pond and a 12 foot swing gate into the area.

Change Orders

The committee approved two change orders.

1. The water line going down West street is on the west side of the road instead of the east side of the road as shown on the town plans. Leighton White now has to cut across the road to tie into the main to feed the irrigation system. This extra work is going to cost $5,991.

2. The School District decided that we need to increase the size of the manhole access cover to the below ground sprinkler system shut-offs. The old design was a 32" circular egress and the new design is a 36" square opening. The cost for this change is $1,627.

Engineering Oversight

We are not going to hire a clerk of the works for the project (to avoid a $54k cost), and try to seek alternative less expensive options to achieve the same results. Mostly this will consist of Mike Trojano and Bill Cooper spending more time overseeing the project at no added cost, but their knowledge is limited in some areas. We are going to hire Bill Davidson from Meridian Land Services to oversee various aspects of the field construction, including the drainage. They would be doing some of this work as part of their normal part of the process, but this is for additional work that is excluded from their normal scope. We will pay him by the hour, and we capped the expense for him at $6k for now.

Interior Work

Most of the work that will be done on the interior is out for bid now. The bids are due back next week, and the committee will meet again on October 25th to review all the bids. We expect to get bids on all the major items such as mechanical and electrical, but there may be some items that get no-bid by everyone. This is a renovation project that will be a pain for some trades to do because of the timing or access issues that have to be dealt with.

We should have an excellent overall view of the cost of the program at our next meeting. We all have our fingers crossed that the bids will come in low, and we will be able to complete the project as originally planned.

Tuesday, August 28, 2007

Milford School Board 8/27/07

High School Renovation Project

The school board met in a special meeting on Monday to review the recommendations of the High School Renovation Committee regarding the bids for the track and field site work.

The board discussed the status of the project and the budget implications of the bids that were higher than expected. Tom Hurley (Committee Chair) updated the board on all the discussions that had gone on at the building committee meeting and the background on all the issues. After all the discussions, the board held two votes.

The board voted 5-0 to award the site work project to Leighton White as per his bid. It is expected that Leighton will start work soon after labor day. Mike Trojano and Bill Cooper will look into the feasibility of doing something with the visitor bleachers (such as moving them to the soccer field), and if it seems viable, to act on the option. If it doesn't appear viable, then they will just be torn down as per the specifications.

The board voted 4-1 (Peter Bragdon in opposition) to authorize the building committee to not hire a Clerk of the Works if the Committee decided not to. This vote allows the building committee to make the decision without having to come back to the School Board for further approval. The vote does not obligate the Committee to not hire a Clerk, but the votes gives it the option to do so.

The board did not act on the award of the track surface bid to Maine Tennis and Track as had been approved by the building committee. The documentation of the bid was not presented at the meeting, and it was felt that it would be better to have the paperwork in front of everyone prior to a vote. This was not a time-critical item like the site-work bid since the track work will not be done until next May or so in any case. The bid information will be summarized and brought to a future meeting for approval.

The cost increase was discussed at length, with the basic consensus being that while it was a problem, it seemed to be of a manageable level given the context of the overall project. We will need to be careful moving forward that we make the proper decisions to keep the project within the overall budget and still have a quality result.

Superintendent Suprenant Contract

The board went into non-public session once the track and field discussion was complete. At the end of the non-public session, it was announced that Superintendent Suprenant and the board had reached agreement on a new three-year contract that is a follow-on to his initial three-year contract that recently ended.

I'd like to publicly thank Superintendent Suprenant for his performance during his first three years with Milford. We have made great progress in that time period, and the Milford School District is in great shape and getting better all the time.

While we don't use these terms to describe it, we have instituted processes that are essentially continuous improvement programs. Continuous improvement as a management philosophy is a prime foundation of quality systems, and we do it well in Milford. An example is our curriculum improvement process that is well entrenched in the district now. Every year we look at portions of the curriculum to plan future changes, we test the options for the changes, and we implement the changes. Each subject area flows thought this process on a regular schedule. This allows us to keep our spending relatively uniform from year to year while at the same time insuring that all aspects of the curriculum are refreshed on a regular planned basis.

We set goals each year, and we measure our progress towards meeting the goals. This closed-loop process helps to insure that we are working on the proper items, that we are coordinating our efforts towards meeting common goals, and that we are communicating our efforts to all interested parties.

Friday, August 24, 2007

High School Renovation Project

We held another meeting last night of the High School Renovation Committee. The purpose of the meeting was to review the bids that came in for "Phase 1" of the track portion of the project. Phase 1 is primarily for the site work and field aspects of the project.

In summary, the budget for the track and field portion of the overall project is $945k, not including any contingency funds or other soft costs. Our current best estimate for this portion of the project (including items that were bid and place holders for items that were not bid) is $1,274k, or $328k higher than budgeted.

This was based on awarding the site work contract to Leighton White, who bid roughly $619k for the site work, while the next lowest bid of the five received was roughly $697k for the same work.

It was disappointing to get such bad news right at the start of the project, but I don't think that it is a killer to the overall project. There are some things that we can do to ease the pain.

While we don't really have a good explanation as to why the bids were so much higher than our planning budget that was used for the budget, our best guess is that the drainage portion of the project ended up being much more complicated than originally envisioned. The final design included a new separate retention area for the water overflow whereas the original thought was that we could just use the retention pond just below the Middle School. The elevations were such that the existing area was too high to make it work, so a new retention area closer to West street was needed.

We made a couple of changes to the project during the meeting to help solve this cost problem. We decided to eliminate the Clerk of the Works position to save $54k. (We did not actually vote to do this at the meeting, but it is highly likely that we will do so at a future meeting.) The position is not really required since we decided to go with a Construction Manager arrangement instead of strictly using a general contractor. The Construction Manager and our own on-site personnel will keep tabs on the project instead. Having a Clerk of the Works might be marginally better than not having one, but it doesn't seem like it is worth the $54k that it would cost.

We spent a lot of time talking about track surfaces. The original plan was for a urethane based surface, and that is what was included in the estimate. We decided to change to a red-colored latex surface instead of going with the urethane surface. The information that we had was that the latex surface would probably need more frequent maintenance actions than the urethane, but the maintenance would be less expensive each time. The urethane might last longer than the latex, but no one could give us any hard numbers as to how long either surface would last. Both surfaces come with a five-year warranty, so from that perspective, they are about equal. Changing to red-colored latex saves $52k in installation cost as compared to the urethane. Latex seems to be the surface of choice for high schools in this area, with Bedford and Pinkerton both planning on installing latex for their recent projects.

We talked about using a blue surface instead of red just to get it to match our school colors, but supposedly the blue color fades fairly quickly while the red seems to be relatively color-fast. We were given a list of 11 schools that had a latex track, and 9 were red and 2 were blue. We decided that color-fastness was more important than matching the school colors.

Eliminating the Clerk of the Works, and changing the track to latex saved a total of $106k, bringing our cost problem down to $223k. The contingency on the project is budgeted at 15% of the construction costs. The 15% contingency associated with the $945k is $141k. If we apply all of that contingency to this portion of the project, then that decreases the cost problem down to $82k. One hates to tap into contingency so early in the process, but that is what it is for so we might as well go for it now since it is needed.

There are still a number of items that are in the cost build-up with a place-holder number that is an estimate and not an actual bid. One of the bigger items is the bleachers, with a place-holder number of $150k for a 680 seat bleacher on the home side and a 320 seat bleacher on the visitor side. This compares to the roughly 400 home/200 visitor set-up we have today. This $150k figure may be more or less once the bids come in. If we really needed the savings, then would could downsize the bleachers a bit to save cost. For example, it was estimated that changing to a 560 home/200 visitor set-up would save about $35k.

The committee voted to award the bid to Leighton White and to therefore move ahead with the project using the current designs. We will have to deal with the remaining $82k cost problem in some manner on the project, but we left that task to a later date once we get better figures for the other items.

The School Board will review this on Monday, and make a final decision on whether to award the contract to Leighton White. Assuming they do, then it is likely that Leighton will start work soon after Labor Day, We are going to have one final home football game at home on August 31st, so he can't start before then. There may be other issues that delay him a bit, but the work should begin soon.

Wednesday, July 18, 2007

Milford - One home football game this year!

We had our first meeting of the High School Project Management Advisory Committee today. The meeting was a good get-to-know-you type of meeting, and it gave everyone a solid understanding of the scope of the project.

One very interesting bit of news that came out during the meeting is that as of now, the plan is to have one home football game held in Milford. All the other "Home" games will be held at a neutral site such as Souhegan.

It now looks like the August 31st game against Souhegan will be held in Milford! This is usually our biggest rivalry, and will be great to have it on our own home turf. We need all the psychological advantages that we can get since they are usually such a tough opponent.

The plan until just recently was that there would be no home games this year. This was needed to allow the track and field renovation plan to move forward at a pace that would enable the project to be complete in time for the fall of 2008 season. There were a bunch of assumptions that led to the project plan being structured this way.

There have been some changes in some of the assumptions, and one is that the Architect (David Laurin) is submitting the site plan review for a "fast-track" approval that, if granted, will allow us to change the sequence of site construction activities and get more things done this year.

I had not heard of the fast-track approval process before now, but supposedly, this process has been used successfully by a few school districts in the past. This process has the potential for turning a permitting process from a couple of months cycle time to less than two weeks.

This is great news if this does occur as is currently planned. It will be nice for the seniors to get to play at least one home game on the home turf, and not miss out on the home field experience in total.